Project building/location: CYBR (Cybersecurity Building)
Project address: 3650 N. Nevada Ave
Construction project manager = Charles Cummings & Carolyn Fox
OIT Construction Coordinator = Greg Williams
Design Phase
- d1. The construction project manager will provide CAD drawings in dwg format to the wireless team.
- PDF construction docs provided. No DWG files have been provided.
- d2. The construction project manager will schedule a meeting with wireless team to discuss rooms with 25+ seats, VIP areas, and ceiling material. This step should occur one to two weeks after d1.
- 2/4/2021 - Cody discussed rooms, ceiling and mounting options with Charles, finalizing placements plans.
- d3. The wireless team will create and provide predictive site survey for wireless access point (WAP) placements to construction project manager. This step should occur one to two weeks after d2.
- 2/4/2021 - Finalized AP placements and enclosure types were provided to Charles. He will ask designers to incorporate them into the design.
- d4. The construction project manager will review and incorporate OIT Construction Standards.
- Construction_Standards_Final > 27 21 33 Data Communications Wireless ACCESS POINTS > 3.01 EXECUTION
- d5. The construction project manager will provide updated CAD drawings with WAP placements to the wireless team.
- 3/15/2021 - 100% CD set has been provided to OIT in the form of BlueBeam link (PDFs). No DWGs have been provided yet.
- d6. The wireless team will verify placements and submit changes if needed to the construction project manager.
- 3/26/2021 - Docs reviewed by Cody and the drop placements looks correct. I did email Charles asking about drop notes that appear incorrect.
Construction Phase
OIT construction coordinator will ensure the following are completed:
c1. Confirm the project is following our construction standards.
including but not limited to two CAT6A lines per WAP, enclosures, grounding, etc...
- c2. Coordinate a box walk with the wireless team and construction project manager once internal framing is mostly completed.
- c3. Provide a date by when the wireless team needs to submit all WLAN quotes.
- c4. The wireless team will provide the quotes to the OIT construction coordinator by the date provided in c2.
- c5. Provide a SpeedType and date by when the wireless team needs to order all WLAN quotes.
- c6. The wireless team will order the quotes and provide receipts to OIT construction coordinator by the date provided in c4.
- Steps c5 and c6 can be skipped if the construction project manager orders the quotes provided by the wireless team.
- c7. Provide a date to the wireless team when the wired lines are pulled to proper locations.
- Date never provided. As of Aug 1 they were still pulling cabling.
- c8. Coordinate a box walk with the wireless team and construction project manager.
- Multiple site visits by Cody checking status of this in July and August
- c9. Provide a date to the wireless team when the terminated lines and enclosures are finished.
- As of Aug 1 all enclosures are installed, but cabling is not complete.
- c10. Confirm ethernet lines have been terminated, tested and labeled.
- c11. Confirm total completion of MDF and IDF; power, lighting, HVAC, racks, cable trays, floor, ceiling, walls, etc.
- 2022-08-10 (DT) MDF and IDF need a lot of work including cables, racks, floor
- c12. Confirm MDF and IDFs doors are secured with a key and the door is not propped open.
- 2022-08-10 (DT) doors are missing the cores plus there is tape over the latch and latch plate
- c13. Confirm switches are racked, powered up and dual connected with a diverse path to both OIT Data Centers.
- 2022-08-10 (DT) Single power, single connect, main data closet doesn't have internet/uccs connection
- c14. Confirm WAP switch ports are configured; 1Gbps or NBaseT ports, descriptions, LLDP and POE+, etc.
- c15. Confirm WAP patch panel ports are patched to switches.
- c16. Confirm we have received the patch panel port label information for each WAP that will be connected.
- c17. Confirm painting is done if required.
WAP Install Phase
- i1. OIT construction coordinator will verify all steps of the construction phase above are completed before starting WAP Install Phase.
- i2. The wireless team will prep and provision WAPs once received.
- i3. The wireless team will install all indoor WAPs.
- i4. The construction project manager will coordinate with the wireless team to assist in installing all outdoor WAPs.
- i5. The wireless team will test WAP functionality and preformance.
Occupancy Phase
- o1. OIT construction coordinator will provide the target date of occupancy to the wireless team.
- o2. The wireless team will add move in day to their calendars and be ready to respond to incidents.
- o3. The construction project manager will provide as-builts to the wireless team.
- o4. The wireless team will perform an active site survey to verify wireless coverage.
- o5. The wireless team will do the following:
- Add or update plans in Airwaves, Ekahau, and OIT file areas.
- Add new switches to Airwaves.
- Update documentation of MDF and IDF, including nearest ladders, etc.
- Update WAPs in the OIT WLAN database.
Version 2019-11-04