Please email wireless@uccs.edu to communicate or provide any files to the wireless team.


Requirements

Before Wireless Access Points can be installed, we need the design and construction phases to be completed.

Design Phase

  • d1. The construction project manager will provide CAD drawings in dwg format to the wireless team.
  • d2. The construction project manager will schedule a meeting with wireless team to discuss rooms with 25+ seats, VIP areas, and ceiling material. This step should occur one to two weeks after d1.
  • d3. The wireless team will create and provide predictive site survey for wireless access point (WAP) placements to construction project manager.  This step should occur one to two weeks after d2.
  • d4. The construction project manager will review and incorporate OIT Construction Standards.
    • Construction_Standards_Final  > 27 21 33 Data Communications Wireless ACCESS POINTS > 3.01 EXECUTION
  • d5. The construction project manager will provide updated CAD drawings with WAP placements to the wireless team.
  • d6. The wireless team will verify placements and submit changes if needed to the construction project manager.

Construction Phase

OIT construction coordinator will ensure the following are completed:

  • c1. Confirm the project is following our construction standards.

    • including but not limited to Two CAT6A lines per WAP, enclosures, grounding, etc...

  • c2. Coordinate a box walk with the wireless team and construction project manager once internal framing is mostly completed. 
  • c3. Provide a date by when the wireless team needs to submit all WLAN quotes.
  • c4. The wireless team will provide the quotes to the OIT construction coordinator by the date provided in c2.
  • c5. Provide a SpeedType and date by when the wireless team needs to order all WLAN quotes.
  • c6. The wireless team will order the quotes and provide receipts to OIT construction coordinator by the date provided in c4.
    • Steps c5 and c6 can be skipped if the construction project manager orders the quotes provided by the wireless team.
  • c7. Provide a date to the wireless team when the wired lines are pulled to proper locations.
  • c8. Coordinate a box walk with the wireless team and construction project manager. 
  • c9. Provide a date to the wireless team when the terminated lines and enclosures are finished.
  • c10. Confirm ethernet lines have been terminated, tested and labeled.
  • c11. Confirm total completion of MDF and IDF; power, lighting, HVAC, racks, cable trays, floor, ceiling, walls, etc.
  • c12. Confirm MDF and IDFs doors are secured with a key and the door is not propped open.
  • c13. Confirm switches are racked, powered up and dual connected with a diverse path to both OIT Data Centers.
  • c14. Confirm WAP switch ports are configured; 1Gbps or NBaseT ports, descriptions, LLDP and POE+, etc.
  • c15. Confirm WAP patch panel ports are patched to switches.
  • c16. Confirm we have received the patch panel port label information for each WAP that will be connected.
  • c17. Confirm painting is done.

WAP Install Phase

  • i1. OIT construction coordinator will verify all steps of the construction phase above are completed before starting WAP Install Phase.
  • i2. The wireless team will prep and provision WAPs once received.
  • i3. The wireless team will install all indoor WAPs.
  • i4. The construction project manager will coordinate with the wireless team to assist in installing all outdoor WAPs.
  • i5. The wireless team will test WAP functionality and preformance.

Occupancy Phase

  • o1. OIT construction coordinator will provide the target date of occupancy to the wireless team.
  • o2. The wireless team will add move in day to their calendars and be ready to respond to incidents.
  • o3. The construction project manager will provide as-builts to the wireless team.
  • o4. The wireless team will perform an active site survey to verify wireless coverage.
  • o5. The wireless team will do the following:
    • Add or update plans in Airwaves, Ekahau, and OIT file areas.
    • Add new switches to Airwaves.
    • Update documentation of MDF and IDF, including nearest ladders, etc.
    • Update WAPs in the OIT WLAN database.