    c1. Confirm the project is following our construction standards.

    •  

      including but not limited to two CAT6A lines per WAP, enclosures, grounding, etc...

  •  c2. Coordinate a box walk with the wireless team and construction project manager once internal framing is mostly completed. 
  •  c3. Provide a date by when the wireless team needs to submit all WLAN quotes.
  •  c4. The wireless team will provide the quotes to the OIT construction coordinator by the date provided in c2.
  •  c5. Provide a SpeedType and date by when the wireless team needs to order all WLAN quotes.
  •  c6. The wireless team will order the quotes and provide receipts to OIT construction coordinator by the date provided in c4.
    •  Steps c5 and c6 can be skipped if the construction project manager orders the quotes provided by the wireless team.
  •  c7. Provide a date to the wireless team when the wired lines are pulled to proper locations.
  •  c8. Coordinate a box walk with the wireless team and construction project manager. 
  •  c9. Provide a date to the wireless team when the terminated lines and enclosures are finished.
  •  c10. Confirm ethernet lines have been terminated, tested and labeled.
  •  c11. Confirm total completion of MDF and IDF; power, lighting, HVAC, racks, cable trays, floor, ceiling, walls, etc.
  •  c12. Confirm MDF and IDFs doors are secured with a key and the door is not propped open.
  •  c13. Confirm switches are racked, powered up and dual connected with a diverse path to both OIT Data Centers.
  •  c14. Confirm WAP switch ports are configured; 1Gbps or NBaseT ports, descriptions, LLDP and POE+, etc.
  •  c15. Confirm WAP patch panel ports are patched to switches.
  •  c16. Confirm we have received the patch panel port label information for each WAP that will be connected.
  •  c17. Confirm painting is done if required.

...