- d1. The construction project manager will provide CAD drawings in dwg format to the wireless team.
- PDF construction docs provided. No DWG files have been provided.
- d2. The construction project manager will schedule a meeting with wireless team to discuss rooms with 25+ seats, VIP areas, and ceiling material. This step should occur one to two weeks after d1.
- 2/4/2021 - Cody discussed rooms, ceiling and mounting options with Charles, finalizing placements plans.
- d3. The wireless team will create and provide predictive site survey for wireless access point (WAP) placements to construction project manager. This step should occur one to two weeks after d2.
- 2/4/2021 - Finalized AP placements and enclosure types were provided to Charles. He will ask designers to incorporate them into the design.
- d4. The construction project manager will review and incorporate OIT Construction Standards.
- Construction_Standards_Final > 27 21 33 Data Communications Wireless ACCESS POINTS > 3.01 EXECUTION
- d5. The construction project manager will provide updated CAD drawings with WAP placements to the wireless team.
- 3/15/2021 - 100% CD set has been provided to OIT in the form of BlueBeam link (PDFs). No DWGs have been provided yet.
- d6. The wireless team will verify placements and submit changes if needed to the construction project manager.
- 3/2326/2021 - Docs reviewed by Cody and the drop placements looks correct. I did email Charles asking about drop notes that appear incorrect.
Construction Phase
OIT construction coordinator will ensure the following are completed:
...