c1. Confirm the project is following our construction standards.
including but not limited to two CAT6A lines per WAP, enclosures, grounding, etc...
- c2. Coordinate a box walk with the wireless team and construction project manager once internal framing is mostly completed.
- c3. Provide a date by when the wireless team needs to submit all WLAN quotes.
- c4. The wireless team will provide the quotes to the OIT construction coordinator by the date provided in c2.
- c5. Provide a SpeedType and date by when the wireless team needs to order all WLAN quotes.
- c6. The wireless team will order the quotes and provide receipts to OIT construction coordinator by the date provided in c4.
- Steps c5 and c6 can be skipped if the construction project manager orders the quotes provided by the wireless team.
- c7. Provide a date to the wireless team when the wired lines are pulled to proper locations.
- Date never provided. As of Aug 1 they were still pulling cabling.
- c8. Coordinate a box walk with the wireless team and construction project manager.
- Multiple site visits by Cody checking status of this in July and August
- c9. Provide a date to the wireless team when the terminated lines and enclosures are finished.
- As of Aug 1 all enclosures are installed, but cabling is not complete.
- c10. Confirm ethernet lines have been terminated, tested and labeled.
- c11. Confirm total completion of MDF and IDF; power, lighting, HVAC, racks, cable trays, floor, ceiling, walls, etc.
- 2022-08-10 (DT) MDF and IDF need a lot of work including cables, racks, floor
- c12. Confirm MDF and IDFs doors are secured with a key and the door is not propped open.
- 2022-08-10 (DT) doors are missing the cores plus there is tape over the latch and latch plate
- c13. Confirm switches are racked, powered up and dual connected with a diverse path to both OIT Data Centers.
- 2022-08-10 (DT) Single power, single connect, main data closet doesn't have internet/uccs connection
- c14. Confirm WAP switch ports are configured; 1Gbps or NBaseT ports, descriptions, LLDP and POE+, etc.
- c15. Confirm WAP patch panel ports are patched to switches.
- c16. Confirm we have received the patch panel port label information for each WAP that will be connected.
- c17. Confirm painting is done if required.
...