Project building/location: ENGR
Construction project manager = Mariness
OIT Construction Coordinator = Greg Williams
| DATE | NOTES |
|
|---|
| May 12, 2022 | Engineering Building Addition - DD package review with Mariness (met in CSB-204) Went over rough floor plans, identified items that need fixed, rooms need moved, etc. |
|
| August 4, 2022 | No updates since the previous meeting. |
|

Design Phase
- d1. The construction project manager will provide CAD drawings in dwg format to the wireless team.
- d2. The construction project manager will schedule a meeting with wireless team to discuss rooms with 25+ seats, VIP areas, and ceiling material. This step should occur one to two weeks after d1.
- d3. The wireless team will create and provide predictive site survey for wireless access point (WAP) placements to construction project manager. This step should occur one to two weeks after d2.
- d4. The construction project manager will review and incorporate OIT Construction Standards.
- Construction_Standards_Final > 27 21 33 Data Communications Wireless ACCESS POINTS > 3.01 EXECUTION
- d5. The construction project manager will provide updated CAD drawings with WAP placements to the wireless team.
- d6. The wireless team will verify placements and submit changes if needed to the construction project manager.
Construction Phase
OIT construction coordinator will ensure the following are completed:
WAP Install Phase
- i1. OIT construction coordinator will verify all steps of the construction phase above are completed before starting WAP Install Phase.
- i2. The wireless team will prep and provision WAPs once received.
- i3. The wireless team will install all indoor WAPs.
- i4. The construction project manager will coordinate with the wireless team to assist in installing all outdoor WAPs.
- i5. The wireless team will test WAP functionality and preformance.
Occupancy Phase
- o1. OIT construction coordinator will provide the target date of occupancy to the wireless team.
- o2. The wireless team will add move in day to their calendars and be ready to respond to incidents.
- o3. The construction project manager will provide as-builts to the wireless team.
- o4. The wireless team will perform an active site survey to verify wireless coverage.
- o5. The wireless team will do the following:
- Add or update plans in Airwaves, Ekahau, and OIT file areas.
- Add new switches to Airwaves.
- Update documentation of MDF and IDF, including nearest ladders, etc.
- Update WAPs in the OIT WLAN database.
Version 2019-11-04